Teleactions maintenance stop in LLA, which retrofit to adapt?

In March 2022, ENEDIS communicated on the subject of the connection of installations to high voltage, and more precisely on the end of maintenance of the ADSL / SDSL network on which some Teleaction (TAC) operate in Analogue Leased Line (ALL).

This technology was historically used for sites requiring H.4 type decoupling protection, but has not been marketed since 2021 and is therefore being discontinued.

The end of operation of the existing LLA links is scheduled for December 2023, and it is therefore necessary to migrate all the LLA TACs to IP (Internet Protocol) links, otherwise the level of protection of the park concerned will be downgraded.

ENEDIS scheme from the Guide to the LLA to IP tele-action migration process

VALEMO, as an expert operator, has developed a turnkey offer to enable its customers to carry out the migrations in time and thus avoid the risk of impacting the production of their installations.

More specifically, the service consists of replacing the two existing boxes at the Delivery Station and Source Station with two new compatible boxes and making the necessary adjustments for optimal operation, in accordance with the following action plan :

  • Carrying out a visual audit of the PoL in order to make an inventory of the existing installations and to identify if they are concerned by its migration. Or study of the photos provided by the client to decide on the need to carry out this retrofit.
  • Delivery of a tailor-made retrofit offer according to the stage of the PoL audit, with full identification of costs, subscription changes, etc.
  • Support in the procedures to be carry out with the various suppliers and service providers (network operator, internet service provider, etc.)
  • General coordination for the order of equipment and the various interventions on site.
  • Supply, commissioning and on-site testing of the new Teleaction in autonomy.

VALEMO having deployed this service to its Operating Customers, now we suggest carrying out this one-off retrofit for our third party clients.

Do not hesitate to contact your usual contact for any further information, or Julien BOURDEAU – 06 35 81 50 13 – julien.bourdeau@valemo.fr

Actualités

RES Services and its partners ensure the maintenance of the offshore wind farm substation in Saint-Brieuc.

Since the end of 2023, RES Services, in partnership with VALEMO, have been deploying their teams on the electrical substation of the Breton offshore wind farm operated by Iberdrola. This collaboration, in which RES Services is the leader, enables the two companies
Lire la suite

Meeting our experts!

Since January, VALEMO has been offering you the opportunity to delve into the heart of our operation and maintenance business by meeting our experts, who have made VALEMO a specialist in the world of renewable energy. Among the experts you can discover:
Lire la suite

Discover the results of our 2023 customer satisfaction survey!

We are pleased to share with you the results of our recent customer satisfaction survey conducted by the Continuous Improvement department. The survey, which was sent to all our customers, attracted a remarkable response rate of 46%, representing 80% of our corporate
Lire la suite