Teleactions maintenance stop in LLA, which retrofit to adapt?

In March 2022, ENEDIS communicated on the subject of the connection of installations to high voltage, and more precisely on the end of maintenance of the ADSL / SDSL network on which some Teleaction (TAC) operate in Analogue Leased Line (ALL).

This technology was historically used for sites requiring H.4 type decoupling protection, but has not been marketed since 2021 and is therefore being discontinued.

The end of operation of the existing LLA links is scheduled for December 2023, and it is therefore necessary to migrate all the LLA TACs to IP (Internet Protocol) links, otherwise the level of protection of the park concerned will be downgraded.

ENEDIS scheme from the Guide to the LLA to IP tele-action migration process

VALEMO, as an expert operator, has developed a turnkey offer to enable its customers to carry out the migrations in time and thus avoid the risk of impacting the production of their installations.

More specifically, the service consists of replacing the two existing boxes at the Delivery Station and Source Station with two new compatible boxes and making the necessary adjustments for optimal operation, in accordance with the following action plan :

  • Carrying out a visual audit of the PoL in order to make an inventory of the existing installations and to identify if they are concerned by its migration. Or study of the photos provided by the client to decide on the need to carry out this retrofit.
  • Delivery of a tailor-made retrofit offer according to the stage of the PoL audit, with full identification of costs, subscription changes, etc.
  • Support in the procedures to be carry out with the various suppliers and service providers (network operator, internet service provider, etc.)
  • General coordination for the order of equipment and the various interventions on site.
  • Supply, commissioning and on-site testing of the new Teleaction in autonomy.

VALEMO having deployed this service to its Operating Customers, now we suggest carrying out this one-off retrofit for our third party clients.

Do not hesitate to contact your usual contact for any further information, or Julien BOURDEAU – 06 35 81 50 13 – julien.bourdeau@valemo.fr

Actualités

A new group of wind farms in Occitanie under VALEMO management

Between mid-2024 and early 2025, VALEMO has begun operating four new wind farms in the Occitanie region: Saint-Amans, Valtoret, Cuxac and Amoures. These wind farms, built in 2024, mark a new stage in the development of our activities in this dynamic region.
Lire la suite

2024: A year of human and international growth for VALEMO

The year 2024 has been rich in achievements for VALEMO, marked by a dynamic of growth and expansion that reflects our ambitions. – A growing teamWe are proud to have welcomed 22 new employees this year. These recruitments strengthen our teams and
Lire la suite

VALEMO supports the energy transition in Greece

By 2030, Greece aims to double its production of renewable energy in certain key regions. The Magoula wind farm, located in Western Macedonia near the town of Kozani, is one of these regions, contributing to this ambitious commitment. VALEMO is proud to
Lire la suite